7 Hot-Tap Tie-in

A hot-tap operation aims at installing tee-branch and valves on a ‘live’ pipeline (still producing while hot-tap is being performed) in order to allow future line connection. The particularity of such tie-in is that it is performed on an existing/producing line which was not initially provisioned for such connection.

Two types of hot-tapping methods are available:

  1. Mechanical hot-tap clamp

  2. Hyperbaric hot-tap

The conventional hot-tap techniques use a clamp to be installed by diver around the pipe. Following sealing (e.g. grout injection) of the mechanical clamp onto the pipe, the hot-tap work can commence.

This report will only describe the latest technique of hot-tap based on hyperbaric welding, which consists in welding on the pipeline a tee reinforcement piece.

Thereafter a vertical valve assembly is mounted onto the tee for subsequent trepanning (or hot-tap) through it. A typical (diver assisted) hot-tap outline procedure is described below. This procedure and the figures are extracted from the hot-tap operation performed on the TOTAL's Frigg UK 32" Gas Trunkline in order to connect the Talisman Energy Ltd Ross 6" Gas Export Line (1998).

Figure 7.1 - Hot-tapping machine and protective structure (lower part) installed on the Frigg Gas Export Line


A typical outline procedure would be as follows:

  1. Hot-tap location

    • Locate the pipeline and the pre-determined hot-tap location (e.g. pipe wall residual thickness)

    • Clear and excavate the seabed for welding habitat installation

    • Remove the pipe coating (e.g. high pressure jetting, concrete wire cutter)

  2. Protective structure installation. The structure has a dual function: (a) as a working template (tee branch installation, habitat support, etc.) and (b) as a protective structure of the tee branch plus valve and piping assembly; once the tie-in has been performed.

  3. Welding operations (see Figure 7.2, “Installation of welding habitat” and Figure 7.3, “Hyperbaric hot-tap welding & assembling process”)

    • Deploy and prepare the habitat (e.g. including the welding and heating modules)

Figure 7.2 - Installation of welding habitat


Figure 7.3 - Hyperbaric hot-tap welding & assembling process


  1. Hot-tap operations (see Figure 7.4, “Hot tap outline operation”)

    Note: For the Ross hot-tap project, a maximum pressure in the Frigg pipeline of 80 bars (i.e. flow reduction) at tie-in location was required during around 5 to 7 days.

Figure 7.4 - Hot tap outline operation


  1. Valve / spool piece installation and work completion

    • Install various equipment (valves, end caps, etc.) required for the future spool tie-in

    • Install the protective structure roof

    • Clear the site and carry out as-built survey.

This operation is generally made with diver assistance and as such cannot be considered as a deepwater operation. However, some contractors are now developing diverless hot-tap systems, e.g. the Deep Tap alliance (Oil States (Houston), Williams, Oceaneering, and T. D. Williamson), Clear Well Subsea, IKM.

Figure 7.5 - The HydroTech diverless hot-tap clamp (Oil States)


Figure 7.6 - Gooseneck Spool and Retrofit Hot-tap Tee (IKM Ocean Design)


Figure 7.7 - Hot Tap Cutting Unit HCTU used for ORMEN LANGE hot taps (Clear Subsea Well)


Figure 7.8 - Deepwater Hot Tap Cutting Unit HCTU used for Asgard hot taps


Most advanced diverless hot taps machine like remotely operated TDW Subsea 1200RC tapping machine can be used for installing hot taps in water depths of up to 3,000 m.

Figure 7.9 - Subsea 1200RC tapping machine (TDW)


loading table of contents...