28 System Integration Testing (SIT)

28.1   General

Further to the EFAT, the Subsea Control System will need to be incorporated with all of the other deliverable components of the SPS package and tested fully as an integrated system. This type of test is called a ‘System Integration Test’ or ‘SIT’.

Planning should be made in the project Schedule for availability of at least one subsea Xmas tree and the template / manifold, so that the overall operation of the system can be verified. (These are not always available at the correct time for 'acceptance testing' of the subsea controls equipment, hence another the reason for the EFAT)

The controls system contract should therefore clearly state the definition of any required system testing and should clarify at what point the equipment is considered 'accepted' from the Supplier. Ideally, this should only be when overall operation of the complete system (including trees, manifold etc) is proven, but this is often difficult to arrange, particularly if the individual schedules are widely separated. In this event, a financial retention is sometimes made, to ensure the eventual testing is performed. In any event, a Warranty Period will cover problems with system operation, but the incentive to correct them in a timely manner must be maintained.

The Client or its Representative should witness the SIT. In order to achieve this, the Supplier must issue a Notice Of Readiness in sufficient time for the Client to mobilise its Representatives, typically, 15 working days is required to mobilise all interested parties for an SIT.

Care should therefore be taken in contractual documentation at the start of a project to ensure these provisions are included, else the Client will find that the last minute changes of schedule and lack of readiness will cause considerable disruption to its other project responsibilities. Similarly, where some tests require the presence of equipment supplied by others, care should be taken to ensure the schedules coincide. Organisation of the SIT is ultimately the contractor’s responsibility, however this test is crucial to verify full and proper communications and functionality of the full Control system when hooked up to Tree and manifold system. Therefore a full understanding of the requirements and a constant overview is required by the client at all times to avoid anything being overlooked.

The SIT is the only opportunity for a Client, its partners, the eventual system Operators and the Installation Contractor, to see all of the SPS equipment operating as it should, prior to being installed subsea. Therefore, significant importance should be placed on the event and the witnessing thereof. Photographs and video records of all aspects of the equipment should be made. All drawings should be checked and marked-up for 'as-built' at this time, as full and correct records will be invaluable once installation commences and for the life of the system. ROV operators in particular should use the opportunity to familiarise their operators with the equipment.

A SIT is usually performed at the manifold / template fabricator's site, or tree supplier, and provision must be made in the respective contracts for access by the controls supplier etc to perform these tests without disruption to the formers' contractual schedule.

28.2   Test Requirements

At the start of SIT, it is assumed that all equipment has already successfully passed the individual Factory Acceptance Testing (FAT) and system EFAT (the availability of the Test Records should be verified).

Therefore, each item can be assumed to operate correctly and interface with its immediate external interfaces. The emphasis of the SIT is therefore to verify that the overall system operates as expected, especially with equipment that has never been connected together as a system before. In particular, that the equipment interfaces correctly with its Installation aids and can be physically installed into position, retrieved, operated by ROV etc.

In general, equipment should be tested for:

  • Mechanical completion and conformance to drawing dimensions.

  • Interfaces with other equipment.

  • Functional operation over the complete range of specified parameters.

Where equipment is missing from the SIT, Simulators should be employed; care should be taken that these have themselves previously been tested as both functional and fully representative of the unit they are simulating.

28.3   Documentation

The proposed test procedure should be written and submitted to the Client for review and approval. No test should be performed until the document has reached an acceptable status; therefore, the first issue should be submitted to the Client at least 6 weeks before the test. A signed, approved copy of the test procedure should be used to perform the test and the test procedure should not then be modified without written permission from the Client; in any event, a corrected document should be issued.

Previous FAT Results should be available.

The results of the SIT procedure should be recorded in a System Integration Test Report document, usually included as an Appendix to the SIT procedure itself. The Report document should then be supplied with the final project documentation.

It should be signed and dated by all witnessing parties.

The report should be written as concisely as possible. However, care should be taken that actual test values are recorded, as well as a statement of PASS/FAIL for each test, so that the document can be used to check differences between identical units, as evidence of drift in parameters, or be used as reference values for other future tests.

All tests should be witnessed by the Supplier's QA department and test results 'stamped' as official records of events.

Ideally, the Supplier should have performed each test procedure at least once, before notifying the Client to attend, so that errors in the procedure are detected at an early stage.

28.4   Test Parameters

The following is a summary of parameters that should be tested as a minimum for a subsea control system. They may be some overlap of testing from the EFAT, however this will be the first time the control system has been interfaced with other equipment from the SPS package i.e. manifold and trees. It cannot be exhaustive, as each system will be different, but again, as stated before, the Client will find that the more testing that can be performed onshore before installation, the better the chances of a trouble-free installation and commissioning.

  • Installation and retrieval of subsea equipment using Running Tools / Installation Frames etc.

  • Operation of controls & valves using ROV.

  • System start up from 'cold' i.e. not pressurised, electrical power off

  • Time to pressurise the system should be recorded, and volume of fluid.

  • No hydraulic leaks throughout the system.

  • All manual valves set to correct positions.

  • ETU correctly displays status of all sensors, valves, subsidiary equipment (HPU, EPU).

  • Preferably pressurise process pipe work to enable operation of all pressure sensors to be verified - this is particularly important where they have been already installed for some time on the Manifold / template and subjected to other pipe work testing by third-parties). Check temperature transducers show nominal ambient readings.

  • Verification of electrical distribution cables and harnesses.

  • All ETU internal parameters correct (voltages, pressures, telemetry system) operational and within expected limits, for all loads from minimum to maximum.

  • Function test Manifold Valves from MCM.

  • Function test all tree valves and choke via manifold interface

  • Verify system can operate every valve and choke without affecting any other valve.

  • Record times to open/close valves and chokes; volumes of fluid required.

  • Verify no other valves move when a valve is operated.

  • Behaviour of system without Subsea Accumulator Module operational.

  • System correctly performs ESD sequences.

  • Record times to perform ESD sequences

  • Verify system behaves correctly for wells in 'Workover' mode

  • Verify historical Database / Trends operate correctly.

  • Verify behaviour of system on failure of one or more power/signal channels, failure of one unit in dual-redundant system (MCS, HPU outputs).

  • Determine limits of operation of system with reduced power supply voltage, reduced system pressures.

  • Verify operation of deliverable test equipment (particularly telemetry monitoring devices).

  • Installation and retrieval of SCM with MRT

  • Verify correct power and communication is available

  • Verify all well identification corresponds to system distribution drawing

  • Function test of Pressure and Temperature Transmitters and Pig detector.

28.5   Post-SIT checks

On completion of the SIT, particular attention should be paid to leaving the system in the correct state for installation and / or operation, such as:

  • All manual valves set to correct position for installation and/or operation.

  • All sensor block valves set to correct position (usually 'open').

  • All alarm limits returned to nominal values (for process parameters) or to correct value for subsea system equipment as specified by the Supplier (HPU, EPU, SCM).

  • Equipment re-packed in offshore transport crates (sealed, protected) if not being immediately installed.

  • No equipment left on manifold / template unless scheduled for installation with it - if so, all hydraulic & electrical connectors to be fixed on their 'parking' plates or suitably protected/greased/fixed down.

loading table of contents...